30 Mount Row
Project Summary
Sector
Residential & Leisure
Client
Summerford Ltd
Value
£18m
Location
Mayfair
Programme
74 Weeks
Status
Completed
Type of work
Basement, Piling, Underpinning, Ground works, Temporary works, Demolition, RC frame

30 Mount Row

Leisure
30 Mount Row | Projects | Forcia

Demolition of an existing building, extensive basement works and completion of Mount Row Gallery together with new prime residential accommodation.

Forcia was chosen by the client due to our proven expertise in structurally complex projects, particularly basement works in Central London.

 
 
Forcia
 
Forcia

The Solution

Our approach entailed an acoustically isolated ‘box-in-box’ construction method, reaching depths of up to 12 metres. Demolition of existing building and the formation of a new basement followed, helped by 10 metre-deep underpins with associated secant piling. Our five-storey reinforced concrete frame would later hold gallery space and residential accommodation, plus a new lift shaft.

The Challenge

We faced a number of key challenges when navigating this extremely logistically complex site, namely managing ground water risk, maintaining stability of the neighbouring structures and working above and in close proximity to the London underground network. While keeping disruption to neighbours to a minimum.

Forcia

The Challenge

We faced a number of key challenges when navigating this extremely logistically complex site, namely managing ground water risk, maintaining stability of the neighbouring structures and working above and in close proximity to the London underground network. While keeping disruption to neighbours to a minimum.

Forcia
Forcia

The Impact

This ambitious project required a multi-faceted approach and a host of technically difficult processes, not least vibration treatment and waterproofing, an RC superstructure, steelwork and the expert management of various risks. We realised the client’s vision to maximise and reimagine the existing space into a contemporary, stunning public gallery and well-appointed apartments.

 
 

The Impact

This ambitious project required a multi-faceted approach and a host of technically difficult processes, not least vibration treatment and waterproofing, an RC superstructure, steelwork and the expert management of various risks. We realised the client’s vision to maximise and reimagine the existing space into a contemporary, stunning public gallery and well-appointed apartments.

 